AFCON 2027, World Athletics 2029 preps face Sh8.38bn funding crisis
Sports
By
Mike Kihaki
| Nov 27, 2026
Ministry of Sports and Sports and Culture committee officials inspecting Raila Odinga International Stadium in Nairobi. [Jonah Onyango, Standard]
Kenya’s preparations to host the 2027 Africa Cup of Nations (Afcon) and the 2029 World Athletics Championships are facing serious financial pressure, with the Ministry of Sports warning that an Sh8.38 billion funding shortfall could undermine its ability to meet international hosting commitments.
This comes at a critical stage of preparations, with major sporting infrastructure projects still awaiting payments, contractors threatening or suspending works and Parliament raising questions over the country's readiness to host thousands of international athletes, officials and fans.
Appearing before the National Assembly Sports and Culture Committee, Principal Secretary Elijah Mwangi said the Ministry requires an additional Sh8.38 billion to meet its recurrent expenditure obligations in the 2027/28 financial year.
READ MORE
Why Kenya's public finance reforms must go beyond legislation
Beverage industry urged to embrace AI, digital innovation to boost productivity
Why are Coast hotels empty while Kenya's tourism numbers climb?
Engineers back nuclear power as Kenya seeks to strengthen energy security
KTN's Kamariki scoops investigative award, dedicates to mentor
KQ sounds 2026 profit warning on rising fuel costs, parts shortages
African lenders tipped on capturing key markets
Jubilee insurance banks on digital transformation to speed up services
The department had requested Sh10.77 billion for recurrent expenditure but received an allocation of only Sh2.39 billion, leaving a deficit of Sh8,384,237,503.
Of the additional funding sought, Sh3.547 billion is earmarked for preparations for Afcon 2027, while another Sh3.9 billion will support the 2029 World Athletics Championships. The balance will cater for other essential departmental operations.
“The higher requirements in FY 2027/28 are for preparation to host Afcon 2027, which is Sh3,546,789,165, and the 2029 World Athletics Championships, which is Sh3.9 billion,” Mwangi told the committee.
The request adds to growing concerns over the financial sustainability of the country's ambitious sporting calendar, particularly as the Government continues to grapple with outstanding payments to contractors undertaking stadium upgrades.
The pressure is also reflected in the overall budget requirements for the Ministry, which has sought Sh42.01 billion for the 2027/28 financial year, comprising Sh10.77 billion for recurrent expenditure and Sh31.23 billion for development programmes.
However, the Budget Policy Statement has provided Sh27.75 billion, leaving an overall funding shortfall of approximately Sh14.26 billion.
The financial constraints are already affecting infrastructure development, with the cost of constructing Talanta Sports City Stadium rising from an initial Sh35 billion to Sh45.8 billion, an increase of Sh10.8 billion.
The 60,000-seater facility, which is expected to be one of Kenya's principal venues during Afcon, had reached 94 per cent completion as of October 1. The main stadium works were 95 per cent complete, outdoor training facilities 92 per cent and external works 93 per cent.
The Ministry of Defence, which is overseeing construction, committed to delivering the facility by December 31, ahead of three months of testing and commissioning.
Despite the progress, Members of Parliament have questioned whether the supporting infrastructure will be ready in time, raising concerns over access roads, spectator movement, hospital capacity, reliable water supply and the protection of playing surfaces against adverse weather.
During an October inspection, Sports Kenya Director-General Timothy Kilimo told the committee that road improvement works had commenced, with seven designated drop-off points planned to ease traffic and spectator movement.
A railway terminus is also under construction next to Talanta Stadium to provide an alternative transport option for spectators.
On water and electricity supply, Kilimo said the facility had been equipped with a one-million-litre water tank, two backup tanks with a capacity of 60,000 litres each and two boreholes. Eight generators are also expected to support operations when the stadium is running at full capacity.
However, MPs want assurances that these installations, alongside medical, security, hospitality and crowd-management arrangements, will be fully operational before the tournament.
The concerns extend beyond Talanta Stadium, with several other facilities earmarked for matches and team preparations also facing financial and construction challenges.
Kasarani stadium will join Talanta as match venues, while Nyayo, Ulinzi and Police Sacco will serve as training facilities. Kirigiti and Utalii grounds have also been designated for referee training.
At Nyayo Stadium, the first phase of refurbishment is valued at Sh1.184 billion, but the contractor had received only Sh200 million, prompting the suspension of works pending payment.
During an inspection by the Senate Committee on Labour and Social Welfare in October, Sports Kenya Deputy Director-General Gabriel Komora disclosed that the contractor was demanding Sh650 million to resume the works.
“Currently, the contractor is asking for about Sh650 million. We have not received this money,” Komora told senators.
Although drainage works, floodlights and CCTV installations have been completed, several critical components remain outstanding. These include connecting the floodlights to the national electricity grid, installing LED screens and a scoreboard, completing perimeter works, turnstiles and ticketing systems, and upgrading facilities for persons with disabilities.
Kipchoge Keino Stadium has a construction and upgrading contract valued at Sh3.51 billion but had received only Sh300 million. Police Sacco Stadium, whose contract stands at Sh713 million, had received Sh50 million, while Ulinzi Sports Complex, contracted at Sh1 billion, had also received Sh50 million.
The payment challenges mirror a wider funding problem previously disclosed by the Ministry. In February 2026, Mwangi sought an additional Sh4 billion to increase the initial Afcon preparations budget from Sh3.5 billion to Sh7.5 billion.
The Ministry subsequently disclosed a Sh14.47 billion deficit, including Sh11.37 billion in outstanding stadium contract payments. Five facilities had contracts worth Sh15.11 billion, against payments of only Sh3.74 billion.
Committee chairman Dan Wanyama challenged the Ministry to demonstrate prudent utilisation of available resources, warning against prioritising international competitions at the expense of domestic sports development.
He said federations were struggling with outstanding debts despite the Sports Fund making progress in supporting national teams.
“The issue of funding national teams was one of the priority things that the Sports Fund must do. So far we are doing well, but federations have issues because you have quite several debts to pay to them, and they are having a lot of problems,” Wanyama said.